Maldives exploring potential of flow batteries on two islands as part of major renewables drive

LinkedIn
Twitter
Reddit
Facebook
Email

The government of the Maldives is seeking input on flow battery-based energy storage systems on two of the country’s 1,192 islands.

The Republic of Maldives Ministry of Environment, Climate Change and Technology (MECCT) said earlier this week (13 November) that an hour-long market sounding session will be held next Monday (20 November).

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The session will discuss the deployment of flow battery systems totalling approximately 6MWh on two outer islands of the South Asian archipelago, as well as energy management system (EMS) technology. The scope of the project will be for the design, supply and installation of the systems.

The online session is being held to gather information and feedback from interested parties and the ministry said in an announcement that it “does not constitute a formal procurement process” at this stage.

The flow batteries would be deployed as part of the Maldives’ Accelerating Sustainable System Development Using Renewable Energy (ASSURE) Project, for which the largest share of funding, US$41.5 million, is being provided by the Asian Development Bank (ADB).

While the flow battery procurement is on a pilot or demonstration project basis, a procurement for around 40MWh of lithium-ion battery energy storage system (BESS) capacity and EMS for deployment on 18 islands was launched in August through the project, as reported by Energy-Storage.news.

ADB said in September as it approved its financing package for ASSURE, which totals US$50.5 million including an US$8.5 million concessional loan from ordinary capital resources and US$500,000 from the Climate Change Fund, that the installation of grid-scale energy storage will help attract private sector investment and enable the local deployment of rooftop, ground mount and floating solar PV.

Meanwhile Japan’s government, contributing US$6.2 million in grant funding to ASSURE through its Japan Fund for the Joint Crediting Mechanism (JFJCM) trust fund within the ADB, said it would be directly funding the flow battery systems as part of microgrids on the islands of Dhidhdhoo and Nilandhoo. In addition the JFJCM funding would also go towards an ocean-based renewable energy (presumably tidal) installation.

The ADB noted in official projects documents that the Maldives is an extremely climate-vulnerable nation, with more than 80% of its land area less than a metre above mean sea level. With its many islands, the country is unable to have a centralised power grid, and instead relies on about 320MW of individual diesel generator-run power plants on 186 of the inhabited islands, and presently about 37MW of solar PV.

That means fuel and therefore electricity costs are high, between US$0.30 and US$0.70/kWh and both the cost of fuel and electricity generation require government subsidies. In 2021, around 1% of the Maldives’ gross domestic product (GDP) was spent on those subsidies, while the cost of diesel itself was equivalent to 7.8% of GDP.

See the government announcement of the sounding session on 20 November, with link to join, here.

Read Next

April 23, 2024
NGK Insulators will provide 72 containerised sodium-sulfur (NAS) battery storage units to a green hydrogen production plant in Germany.
April 23, 2024
Croatia will provide some €500 million (US$534 million) in subsidies for battery energy storage system (BESS) technology, a government minister said.
April 22, 2024
Dutch developer Giga Storage has received a permit for construction for its 600MW/2,400MWh BESS project in neighbouring Belgium and will choose the BESS technology provider after summer.
April 19, 2024
System integrator Flexgen has partnered with IPP Arclight and its subsidiary Infinigen Renewables to deploy a PV co-located 15MW BESS project in Puerto Rico.
April 18, 2024
Clearway Energy has put two large solar and storage projects into operation in California, it announced on the same day as an industry letter asking Congress to reform siting, permitting and transmission before this year’s elections.