The Energy Storage Report 2024

Now available to download, covering deployments, technology, policy and finance in the energy storage market

Genex achieves contractual close for 100MWh Queensland battery project

LinkedIn
Twitter
Reddit
Facebook
Email
Genex solar farm in Kidston, Queensland, close to the site of the 2GWh PHES plant the company has under construction. The 50MW PV facility pictured is being expanded to 270MW to integrate with the pumped hydro. Image: Genex.

Clean energy developer Genex Power has “secured the final piece” of its project finance package for the 50MW/100MWh Bouldercombe Battery Project (BBP) in Queensland, Australia. 

Genex made an announcement to the Australian Securities Exchange (ASX) this morning. Having received firm commitments to a AU$40 million (US$29 million) capital raise to fund the project, it has now achieved contractual close for the standalone battery energy storage system (BESS). 

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The announcement comes just two days after Energy-Storage.news reported that Genex had agreed a AU$35 million debt finance facility for BBP from specialist project finance fund manager Infradebt under a 12-year term.

Tesla will supply 40 of its Megapack grid-scale battery storage units to the project and the US tech company’s Autobidder trading and bidding platform will control its market-facing activities. 

Genex said the AU$40 million institutional placement, alongside the Infradebt loan, will go towards project construction costs as well as repay an existing debt facility to Australia’s national Clean Energy Finance Corporation and provide further working capital. 

“I am delighted to announce today the final piece for the project financing of the Bouldercombe Battery Project, being the completion of a AU$40 million institutional placement,” Genex Power CEO James Harding said, thanking the company’s existing institutional shareholders and welcoming new ones. 

“In acknowledgement of this support, I am pleased to confirm the launch of a AU$10 million Share Purchase Plan to allow our retail shareholders to participate in the capital raising on similar terms to investors under the institutional placement.”

Bouldercombe, along with Genex’s large-scale pumped hydro energy storage (PHES) plant under construction at Kidston, also in Queensland, “will add significant upside exposure for shareholders when it commences operation,” scheduled for mid-2023, Harding said. 

Read Next

April 16, 2024
Energy management solutions provider GridBeyond has raised investment to extend its capabilities for “robotic” trading of energy assets and expand internationally, the company’s CEO has said.
April 16, 2024
SSE Renewables has launched its first operative battery energy storage system (BESS) with a capacity of 50MW/100MWh. 
April 15, 2024
Australian energy minister Chris Bowen has said tenders for 500MW of renewable energy backed with energy storage will open in the middle of this year in Western Australia (WA).
Premium
April 12, 2024
This Friday Briefing takes a look at how residential battery storage and other DERs can be a force for the greater grid.
April 11, 2024
A Quinbrook Infrastructure Partners portfolio company will shortly begin construction on a 250MW/500MWh battery storage system in Queensland, Australia.

Most Popular

Email Newsletter